The rendering is in, and this is it...
But we are left to guess what the plan will be. This is my guess, and this looks like a Billion Dollar project.
Below is my guess on what the plan is...
Phase 1: September 2024 to September 2027
-Close the parking lot, begin construction on the arena.
-Take steps to protect Japan-town, the Japanese garden and the Japanese Church of Christ
-Close and demolish the Radisson Hotel
-Close and demolish the Fidelity field office
-Close and demolish the west wing of the Salt Palace (West of 200 W.) while preserving the rest of the facility
-Begin construction on the south plaza and the pedestrian bridge
-Take steps to protect Japan-town, the Japanese garden and the Japanese Church of Christ
-Close and demolish the Radisson Hotel
-Close and demolish the Fidelity field office
-Close and demolish the west wing of the Salt Palace (West of 200 W.) while preserving the rest of the facility
-Begin construction on the south plaza and the pedestrian bridge
Phase 2: Late 2034-and beyond
-Close and demolish the original Delta Center
-Build a tunnel under or bridge over 300 West
-Build a
-Build a tunnel under or bridge over 300 West
-Build a